Sign Up

Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.

Have an account? Sign In

Have an account? Sign In Now

Sign In

Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.

Sign Up Here

Forgot Password?

Don't have account, Sign Up Here
Sign InSign Up

Solar Faqs

Solar Faqs Logo Solar Faqs Logo
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Home
  • Contact Us
Supported By
Home/ Questions/Q 337
Next
In Process
aalan

Solar Faqs Latest Questions

Yash
  • 0
Yash
Asked: May 29, 20242024-05-29T14:32:48+05:30 2024-05-29T14:32:48+05:30

Why is the price of solar power higher in corporate PPAs when we compare with utility scale government tenders from SECI etc?

  • 0
Why is the price of solar power higher in corporate PPAs when we compare with utility scale government tenders from SECI etc?
Share
  • Facebook

    1 Answer

    • Voted
    • Oldest
    • Recent
    1. Prasanna Singh
      Prasanna Singh
      2024-05-29T14:34:11+05:30Group Editor, Saur Energy International | Answer on May 29, 2024 at 2:34 pm

      That’s a very good question, and we will try and answer it as comprehensively as possible here. Corporate PPAs in India have typically been at a 50 percent or higher premium over bids at government backed tenders, and for good reasons. Right at the top is the matter of scale. The low rates of Rs 2.50 and around that you see for solar tenders are for capacities that typically are in the 100 MW plus range, at the least.

      Secondly, government tenders come with significant flexibility on location, something most corporate PPAs don’t. In a majority of cases, particularly large solar rooftops, the installations have to be in the same state or even corporate plant site. That impacts generation.

      Then we have the issue of long term government PPAs versus corporate ratings, which affects cost of funds for the developer. Funds are typically raised for shorter tenures, at higher costs in case of corporate PPAs.

      Finally, project timelines in government tenders are 24 months or higher, allowing developers to make the most of buying opportunities for key inputs like modules. In corporate deals, project timelines can be as little as 6 months, forcing developers to move faster with limited flexibility.

      All of these add up to a significantly higher cost, and this is before taking into account multiple charges at state level open access regulations, versus supplying to discoms directly.

      • Reply
      • Share
        Share
        • Share on Facebook
        • Share on Twitter
        • Share on LinkedIn
        • Share on WhatsApp
    Leave an answer

    Leave an answer
    Cancel reply

    Sidebar

    Experts Panelist

    Swapanil Wakade, Ecofy

    Swapanil Wakade, Ecofy

      Sai Charan Kuppili, Jinko Solar

      Sai Charan Kuppili, Jinko Solar

        Manjunath AR Global Product Manager, Fimer

        Manjunath AR Global Product Manager, Fimer

          Questions Categories

          Solar Module
          Policy and Schemes
          Solar Inverter
          O&M
          Solar Plant
          Solar Structure
          Renewable Energy
          Supported By

          Footer

          © 2024. All Rights Reserved.